PROJECT:
AKSA - POWER PLANT A Turkey & Uzbekistan
Contract
|
EPC,CCPP RELOCATION PROJECT
|
Employer
|
Aksa Enerji Üretim A.Ş.
|
Contract Begin
|
20.11.2020
|
Contract End
|
20.01.2022
|
Location
|
ANTALYA, TURKEY – TASHKENT, UZBEKISTAN
|
DETAIL:
Completing disassembly of 4 gas turbines, 4 steam boilers, 2 steam turbines and generator for combine cycling, 3 transformers, all auxiliary equipments and complete steel construction and piping of 240 MW combined cycle power plant, as well as its cleaning, painting, packing and transportation operations to Uzbekistan in 4 months.
Completion of positioning and assembly of 21.022 tones of steel constrcution, 2057 DI steam boiler welding, 4166 m x 4 tank welding, installation of two 12480 m3 water cooling tower, 7350 m2 panels and 54 bop quipment installation, 47109 DI piping operations and activation of power plant for energy production.