PROJECT:
AKSA - POWER PLANT B Turkey & Uzbekistan
Contract
|
EPC,CCPP RELOCATION PROJECT
|
Employer
|
Aksa Enerji Üretim A.Ş.
|
Contract Begin
|
30.03.2021
|
Contract End
|
30.04.2022
|
Location
|
Manisa/TURKEY – Van/TURKEY – TAŞKENT/UZBEKISTAN
|
DETAILS:
Disassembly of 2 combined power plants, located in Manisa and Van, 115 MW each, with a total of 230 MW energy production capacity, including; 24 gas motors, 24 steam boilers, 2 steam turbines and generator for combine cycling, 2 transformers, all auixilary equipments, steel construction, 1140 electricity panels, 385000 meters of cabling, 1280 instruments, and completion of cleaning, painting, packing and transporting operations to Uzbekistan in 80 days.
Assembly and combination of 2 combined power plants into one, including; 15427 m3 concreting, 1252 tones of iron chelation, construction of 7812 m2 closed area, 1200 tones of steel construction setting and welding, installation of 24 steam boilers, five 1604 meters tanks, and 6240 m3 water cooling tower, as well as mounting of 65 bop equipment, 630 electricity panels, 290000 m cabling and activation of the power plat for energy production with respect to national standards and guidelines.