2023-2024 & Tekirdağ, Türkiye
MUREL DEMİR ÇELİK TİC. A.Ş. HAYRABOLU WIRE MESH STEEL PRODUCTION FACILITY
Project Information
EMPLOYER
Murel Demir Çelik ve Ticaret A.Ş.
LOCATION
Tekirdağ / Türkiye
CONTRACT DATE
26.05.2023
COMPLETION DATE
30.09.2024
SCOPE OF WORK
Construction, Electrical, Mechanical, and Commissioning Works
Project Details
Between 2023 and 2024, Murel Demir Çelik ve Ticaret A.Ş. undertook the Hayrabolu Wire Mesh Steel Production Facility project, with Murel Yatırım İnşaat A.Ş. responsible for the construction, mechanical, electrical, and commissioning works.
With the completion of Phase 1 of the investment, Murel Demir Çelik A.Ş. operates a facility in the Hayrabolu Organized Industrial Zone with a 57,657 m² footprint area. The facility includes 8,000 m² of covered area and produces 100,000 tons of steel mesh and 105,000 tons of cold-drawn rods annually.
Scope of Work:
- 8,200 m³ of excavation
- 7,250 m² of formwork
- 32,000 m³ of concrete works
- 418 tons of construction rebar
- 23,000 meters of cable installation
- Installation and termination of 33 electrical panels
- Hot water, sanitary, and fire-fighting installations
- Landscaping works